Week #79
Week #78
Week #77
Week #76
Week #75
Week #74
Week #73
Week #72
Week #71
Week #70
Week #69
Week #68
Week #67
Week #66
Week #65
Week #64
Week #63
Week #62
Week #61
Week #60
Week #59
Week #58
Week #57
Week #56
Week #55
Week #54
Week #53
Week #52
Week #51
Week #50
Week #49
Week #48
Week #47
Week #46
Week #45
Week #44
Week #43
Week #42
Week #41
Week #40
Week #32
Week #31
Week #30
Week #29
Week #28
Week #27
Week #26
Week #25
Week #24
Week #23
Week #22
Week #21
Week #20
Week #19
Week #18
Week #17
Week #16
Week #15
Week #14
Week #13
Xmas Break
Week #4
Week #3
Week #2
Week #1

Thai Refit Summary

These are the weekly summaries of the work that was completed on Ocelot, in chronological order.
Newest entries are at the bottom.

Month   1: Week 1 Week 2 Week 3 Week 4 Oct 24 - Nov 20, 2011
Month   2: Week 13 Week 14 Week 15 Week 16 Jan 16 - Feb 12, 2012
Month   3: Week 17 Week 18 Week 19 Week 20 Feb 13 - March 11, 2012
Month   4: Week 21 Week 22 Week 23 Week 24 March 12 - April 8, 2012
Month   5: Week 25 Week 26 Week 27 Week 28 April 9 - May 6, 2012
Month   6: Week 29 Week 30 Week 31 Week 32 May 7 - May 31, 2012
Month   7: Week 40 Week 41 Week 42 Week 43 Aug 6 - Sep 2, 2012
Month   8: Week 44 Week 45 Week 46 Week 47 Sep 3 - Sep 30, 2012
Month   9: Week 48 Week 49 Week 50 Week 51 Oct 1 - Oct 28, 2012
Month 10: Week 52 Week 53 Week 54 Week 55 Oct 29 - Nov 25, 2012
Month 11: Week 56 Week 57 Week 58 Week 59 Nov 26 - Dec 23, 2012
Month 12: Week 60 Week 61 Week 62 Week 63 Dec 24, 2012 - Jan 20, 2013
Month 13: Week 64 Week 65 Week 66 Week 67 Jan 21 - Feb 17, 2013
Month 14: Week 68 Week 69 Week 70 Week 71 Feb 18 - March 17, 2013
Month 15: Week 72 Week 73 Week 74 Week 75 March 18 - April 14, 2013
Month 16: Week 76 Week 77 Week 78 Week 79 April 15 - May 12, 2013
Positioning Ocelot above the trailer
Positioning Ocelot above the trailer

Week 1, October 24 - 30, 2011:
We sailed down from Yacht Haven at the northern end of Phuket Island to Ao Chalong Bay in the SE corner of Phukiet, and started preparing Ocelot - taking EVERYTHING out of all the lockers and putting them into big plastic storage containers.  We also removed all the sails and even the boom!  Started our contract with Golf, our main contractor, and gave him a down payment so he could start buying materials.  Bangkok is currently flooded, so some things have to be bought quickly, before they're no longer available.  Manoon, the Coconuts boatyard manager, came out to inspect Ocelot and on Thursday he hauled us out with only a few heart stopping moments (like the 16 knot wind from the quarter pushing us sideways, and when a rope got caught in the propeller and had to be cut free).  Then Golf's team descended on Ocelot and started tearing the teak decks off her, as we started transporting everything to Golf's workshop for storage.  On Saturday the crane arrived and took out Ocelot's mast (along with the masts of 2 other boats).

Goodbye teak on starboard bow, Coconuts Boatyard, Phuket, Thailand
Goodbye teak on starboard bow

Week 2, October 31 - November 6, 2011:
Erected a huge tent over Ocelot that Golf had bought with our seed money.  Workers used paint stripper to remove much of our bottom paint, and all deck hardware, including 19 hatches, were removed as the teak continued to be removed.  More packing up of cushions, mattresses, etc, and several trips to Golf's workshop to store it all.  Started stripping the mast and boom of all the steps, ropes and other fittings.  We lowered Tomcat (our dinghy), flushed the engine, and took all it to the workshop.  All fittings were removed from the cockpit, as well as the teak decks.  The transoms were ground back and the woodworker started building a mold to extend the transoms.

Pulling the wood mold off the starboard extension
Pulling the wood mold off the 1st starboard extension

Week 3, November 7 - 13, 2011:
Golf's team started removing the varnish from Ocelot's interior with a heat gun.  Jon removed all of the headliners from the salon as well as all the cabins and they were all taken to the workshop for storage.  Meng, our woodworker, started repairing the whale damage in Amanda's cabin.  With the teak removed from the deck, the workers started grinding off the mastic that was under the teak, as well as grinding off the gelcoat on the cabin-top.  A plywood frame for Ocelot's transom extension was built, waxed, and 6 sheets of heavy fiberglass was laid in it before the plywood was cut away.

Ocelot sitting under her new tent home, with her mast out
Ocelot sitting under her new tent home, with her mast out

Week 4, November 14 - 20, 2011:
We bought Golf a cute shop-vac so he can vacuum up all the dust from all the grinding.  Stripped all the winches and spin-locks off the top of the salon and targa bar.  Removed more fittings and mast steps from the mast and boom.  Removed the engine controls, all of the outside instruments, and the engine instruments.  We suspended our roller head‑stay as well as our cap‑shrouds from the tent frame, to get them off the sand.  Decided that the transom extension was fatally flawed and had it cut off.  Started peeling back some of the deck, where it had delaminated from the balsa coring.  This eventually led to the entire deck and coring being removed, which was not in the original plan.  Tragically, Golf's sister was in a motorcycle accident with a truck and eventually died, with Golf inheriting her 2 younger children.  But he also got his truck back from the shop, with its brand new several thousand watt sound system.


Break while Jon and Sue fly home for Thanksgiving and Christmas, November 21, 2011 to January 15, 2012


Inside of the port hull, with antifouling paint scraped off
Inside of the port hull, with antifouling paint scraped off

Week 13, January 16 - 22, 2012:
Workers continued to remove Ocelot's antifouling paint (and underlying gelcoat!) with grinders.  The top layer of the deck was removed and the decision made to remove the balsa as well, and replace it with (inorganic) foam, so workers started chiseling out the balsa.  Some finish work was done in the cockpit, fairing it after the teak was removed.  Other workers were inside, sanding off the varnish (most doors had been removed while we were away).  Golf even started applying some varnish to some small bits of flooring.

Removing the stove, with the sinks already out
Removing the stove, with the sinks already out

Week 14, January 23 - 29, 2012:
Our new woodworker, Houa, arrived and started tearing apart the drawer cabinet by the entryway.  He also started on the galley, removing the stove, oven, and the entire sink cupboard.  Jon removed several fittings from the top of the targa bar, like the mainsail track.  Foam sheets were bought and sections cut and fitted to the depressions where the balsa had been.  Golf tried epoxying down a couple of foam sheets, but without using polyethylene sheeting, so we bought him some polyethylene and showed him how to use it.  We eventually settled on a hybrid between our 2 methods of putting the decks back, putting fiberglass and foam down in one operation, and then applying the top coats of glass the next day.  Grinders continue to work on the underwater sections of the hulls, finishing starboard side and starting on port.

Laying in the foam for the deck, above an extra layer of bi-axial glass
Laying in the foam for the deck, above an extra layer of bi-axial glass

Week 15, January 30 - February 5, 2012:
Of the 15 deck patches that need to have foam cut to fit and epoxied down, we got 7 of them done, plus 4 smaller cockpit patches finished.  Jon foamed the line to the fridge to keep it from condensing.  Our carpenter finished building the drawer cabinet next to the fridge and started fitting our new stove and oven.  This will be a challenge as the stove is 3" (7cm) deeper than our previous stove and oven, and we don't really have the room to spare.  Jon got more of the mast disassembled, including removing our "diamond stays".  Several of our floorboards got sanded at Golf's workshop, about 3 miles (5km) from the boatyard (and owned by the same family).  Ocelot's bottoms got ground off until they're almost completely free of antifouling paint and gelcoat.  A good week!

Epoxying down the foam over the port forward cabin
Max, Golf & E-U sticking down the foam over the port forward cabin

Week 16, February 6 - 12, 2012:
We got another 5 of our 15 deck‑patches foamed and covered in 3 layers of biaxial glass, including our 2 most challenging areas over the forward cabins, so we only have 3 more to go, all at the back of Ocelot.  Our 2 push‑pits were removed (a major undertaking) and 2 problem areas that were under them were opened up and the balsa removed.  We started reinforcing the glass under the deck but this still has a long way to go.  The targa bar was stripped of all fittings (except the solar panels) so it's ready to be refurbished.  The design for our new rigid bimini was reworked to be simpler and stronger.  The oven area was opened up, the oven fitted, and we now have a plan for putting it all back together.  The drawer area by the entryway has been prepped for varnishing, and the varnishing of all our doors and floor panels has finally begun in Golf's workshop.

Golf laying 3 strips of glass in increasing widths
Golf laying 3 strips of glass in increasing widths

Week 17, February 13 - 19, 2012:
The foaming and glassing of the side decks was almost completed - all the foam was put down and glassed over, the hatch openings reinforced, and several strips of reinforcing glass were laid along the edges of the decks.  All that remains is to fair the side decks and then cover them with the final 2 layers of biaxial glass.  Houa is extending the entire port side of the galley by a few inches to make the new stove and oven look like they belong.  He's building a new drawer under the oven and creating a new door for the storage area next to the stove and sink.  Hem, our mechanic, took the injectors, injector pumps, heat exchangers, water‑injection elbows, exhaust manifolds, freshwater pumps, and saltwater pumps off both engines.  He also took the whole head off starboard engine.  These will be serviced and reinstalled.  We would have gotten more done this week but Golf has been having severe back and leg problems with his sciatic nerve, which has been painful enough for him to go to the hospital.  We certainly hope he's feeling better soon!

Long-boarding the topsides, with a crab watching...
Long-boarding the topsides, with a crab watching...

Week 18, February 20 - 26, 2012:
Although the week started off with a bang, it ended with a bit of a whimper, and we didn't get quite as much done as we'd hoped.  Jon managed to get all the gear off the foredecks, including the 2 pulpits, the massive fore‑beam, the anchor platform, and the stubborn plate that holds the aft end of the anchor platform to Ocelot's bow.  Jon and Golf designed the new mechanism for holding Ocelot's trampolines, which should be stronger and more aesthetic than our old sail‑track system.  The guys started to lay down the epoxy fairing compound that's to go under the final layers of fiberglass on deck, but they weren't able to finish fairing it smooth.  Houa managed to get the new stove and oven installed, but he's spending a lot of time on fiddly little bits like the new drawer under the oven.  We appreciate all the work he's putting in and we really appreciate the quality of his work, but we also have lots of other things for him to do.  More guys joined the team and started sanding the topsides in preparation for painting them.  Looking at other boats around us, it can take a long time to get the hulls as flat and smooth as we'd like them.  Finally, they started working on the strip behind the cockpit, the last area of the deck that needs the foam sandwich rebuilt.

Golf & Max chiseling out the old balsa behind the cockpit seat
Golf & Max chiseling out the old balsa behind the cockpit seat

Week 19, February 27 - March 4, 2012:
A good week!  The final 2 sheets of biaxial glass were laid down on both the port and starboard side‑decks.  We've been waiting for this for a long time!  The decks look and feel great.  We also put down our 15th and (hopefully) final long strip of foam behind the cockpit  We got our headstay down from the tent rafters and Jon started disassembling it.  The replacements for our water‑damaged headliner pieces were cut out and epoxy coated.  The floorboards got their first coats of varnish.  Both topsides were sanded and several gelcoat cracks were ground back and explored before being glassed up and covered over with epoxy fairing compound.  Some hull‑deck joint‑lines at the bows were cleaned up and glassed over to strengthen them.  But we also found more wet balsa to replace in the floor under the cockpit table and behind the aft cockpit seat.  Nice to have more reconstruction than deconstruction!

Baw touching up the floorboards with lightly colored varnish
Baw touching up the floorboards with lightly colored varnish

Week 20, March 5 - 11, 2012:
Most of the work this week was in the cockpit.  We stripped off the top layer of fiberglass for most of the cockpit floor, ground back the gelcoat, dug out the old balsa coring, replaced it with structural foam, and glassed it over in 3 separate places: under the cockpit table and on both sides of the cockpit.  We also opened up the steps going down to the companionway, chasing down rotten balsa coring.  This work is still ongoing, but we're hopeful that we're nearing the end of the surgery.  Jon started cutting cores out where the deck hardware (winches and such) bolt through the cabin‑top, so we can reinforce those areas where bolts go through the coring.  In the woodshop, Houa finished repairing those floorboards that needed it, and many of the floorboards got several layers of varnish.  Those that got repaired also had the wood tinted to match our existing wood.

Max & Golf lifting away Ocelot's instrument console
Max & Golf lifting away Ocelot's instrument console

Week 21, March 12 - 18, 2012:
This was a week of investigative surgery to remove damaged wood.  Much of Ocelot's entryway wood was removed, as well as a strip of the salon floor under the navigation station and the entire helm area.  But most of the floorboards got all of their coats of varnish, and Golf's happy with the quality of the work.  Workers started long‑boarding the hulls in preparation for spraying them.  The bows got reinforced with fiberglass and epoxy mud, and an area to the right of the entryway was re‑glassed.  Two of our big cockpit hatch‑covers were stiffened wonderfully with foam and fiberglass and the other 4 are being worked on.  Work has started on stripping our fore‑beam and other aluminum fore‑deck bits in preparation for painting them, and Jon drilled out almost 100 cores around existing bolt holes in our cabin top so they can be filled with epoxy mud, re‑glassed, and the holes re‑drilled.

Ocelot sitting under her shady tent, being worked on
Ocelot sitting under her shady tent, being worked on

Week 22, March 19 - 25, 2012:
A productive week.  Both bows had 7 strips of foam bonded on, which was shaped to sharper points than before and eventually covered with 7‑8 layers of biaxial glass.  The salon sub‑floor under the nav‑station was rebuilt in glassed in foam, with cute foam and fiberglass supports.  Six big hatch‑covers, 4 from the cockpit and 2 from the chain lockers, were ground back and had foam and 2‑3 layers of biaxial glass stuck on underneath.  This has strengthened them wonderfully.  The outer hulls were sanded and the hole by the starboard forward portlight was filled, then the guys started sanding the inner hulls and under the bridge‑deck.  The speed and depth transducers were removed and their through‑holes checked and cleaned.  Boy started repairing the aft cockpit seat with glass and foam on top of the backrest, and we moved our workshop out from under the neighboring catamaran and into a small tent.  The 2 forward ports in the salon were removed (with great difficulty) and much of the area in front of them had to be opened up as the drain‑pipes for the grab‑rails have leaked, but we found 2 big stainless steel tanks that we didn't know we had!

Houa working on the port-side transom extension
Houa working on the port-side transom extension

Week 23, March 26 - April 1, 2012:
The week started off with a bang but ended with a bit of a whimper.  Max worked on the entryway all week, first building and installing a beam for our sliding door to sit on, then building supports and the floor just outside the door and installing them, then fitting and installing foam on the steps to the cockpit and finally cutting and shaping the foam for both sides of the steps.  Our new trampoline holders were glassed on up front, and Baw built foam fillers for the cutouts under our emergency hatches and glassed them in.  The big news is that Golf started both transom extensions, but after making good progress, that work has stalled while they figure out how to make the 2 sides the same.  Boy ground off all the gelcoat on both transoms in preparation for installing new steps and side‑walls.  Jon got the mast stripped and all the wires out, so mast, boom, and forebeam are all ready for sanding and painting.  The long‑borders have been working all around the hull and she's looking very smooth.

Jon & Baw sticking down the top of port extension
Jon & Baw sticking down the top of port extension

Week 24, April 2 - 8, 2012:
Houa used forms to bend each transom extension to be the same shape, then the team glassed them to that shape.  They built and installed a central spine and 5 frame pieces (4 half‑frames and an end piece) in each extension, trimmed them down carefully to slope them correctly, and covered them with foam to completely enclose the extensions.  Port extension got wrapped in 3 layers of biaxial glass while starboard was used to shape the foam for the outer wall leading down to the extension.  Max and his brother Lek foamed both sides of the entryway and then glassed in the whole entryway area, including the steps.  Jon removed both rudders and polished them up so we can install bigger lower bearings for them.  Jon and Sue went to Bangkok and Phuket Town to get "retirement" visas that let them stay in Thailand for 1 year.  Jon turned 57 on Saturday so we hosted a fun party with lots of food and drink.

The organized pandemonium of work on Ocelot
The organized pandemonium of work on Ocelot

Week 25, April 9 - 15, 2012:
A productive week, despite losing 2 days to the Thai New Year celebrations.  Friday is Thai New Year (Sonkram) so nothing happens Friday or Saturday except spraying people with water and other forms of celebration.  At the helm, Max got the whole helm area foamed in, which involved 5 complicated bits of foam.  He used the existing inner layer of fiberglass as a form, but it was so flimsy that it needed significant reinforcing before he could stick foam to it.  Jon then de‑cored the area where the steering gearbox bolt on, cutting away the foam so it can be filled with epoxy mud.  Max also cut out a section of bad balsa from the long wall between the galley and the battery compartment.  At the sterns, the starboard transom extension was glassed in to match the port side.  Then work started on the outer walls coming down to the new swim platforms.  The inner and outer skins of both walls were built and epoxied down, as well as 5 internal strengthening webs.  On Friday, Golf and his wife took Sue on a tour of the Sonkram celebrations and then took her to a sumptuous lunch - Jon would have loved to go as well, but he was feeling ill that day.

Ocelot being worked on - click for larger view
Ocelot being worked on - click for larger view

Week 26, April 16 - 22, 2012:
Both walls going down to our transom extensions got their insides glassed with 3 layers of biaxial glass, and the port side wall was cut down to the correct size and shape before getting (most of) the top put on.  Max glassed in all the exposed foam around our helm, and also cut out a section of wall under our helm, foamed it, filled Jon's de‑coring holes with epoxy mud, glassed it in, and painted it with gelcoat.  Houa started working on the area in front of the salon, cutting open our new "secret compartments" and planning how we'll restore the area.  Jon started disassembling our bimini and planning how to build a new, solid bimini.

Baw mudding up the top of the starboard wall
Baw mudding up the top of the starboard wall

Week 27, April 23 - 29, 2012:
Both of the newly discovered forward compartments got their walls repaired and their insides gelcoated, then Max started replacing the balsa above them with foam, getting 3 good pieces of foam put down on each side.  Max also replaced a plywood backing plate in the cockpit with several layers of glass and epoxy mud.  The starboard‑side wall going down to the new swim‑platforms got entirely foamed and shaped.  The port‑side wall got a bundle of foam epoxied into the outer edge so it can be shaped correctly.  Our rudders were taken to Luk Engineering to be reworked, and the sail‑drive lower gear‑cluster was given to Hem to be reworked.  The steering gear was remounted at the helm, marking our first reassembly.  The battery area had the rotten wood removed and work has started rebuilding it, marking (hopefully) the last of the disassembly.  Jon serviced the autopilot drive but found it needed some cracked parts replaced.  Last but certainly not least, Golf has started going to a chiropractor to help straighten out his previously broken back.

Lek epoxying the first layer of fiberglass onto our starboard wall
Lek epoxying the first layer of fiberglass onto our starboard wall

Week 28, April 30 - May 6, 2012:
Our boom, forebeam, and other spars got cleaned of paint and were taken to the metalworker for some welding work.  Our port wall down to the transom got its final bits of foam and was trimmed down to shape, with holes for where the railing will bolt down.  The starboard wall not only got shaped but was covered in 4 layers of biaxial glass.  Our mechanic worked much of the week putting our starboard engine back together again.  A cut that was made down the length of both decks in November was finally patched with strips of reinforcing glass under the deck.  Houa glassed over the foam in the battery area and started crafting a rail to hold our battery straps, to hold our batteries in place.  Max continued foaming in the areas in front of the salon where the wet balsa was removed.  But Friday and Saturday were a bit of a washout (literally) as it rained hard for much of the time.

Max & brother Lek glassing the back of the cockpit seat
Max & brother Lek glassing the back of the cockpit seat

Week 29, May 7 - 13, 2012:
During week 29 of our Thai Refit, the port‑side extension finally got glassed in, but then Baw left the team.  Three strips of glass were laid under the deck, at the hull‑deck joint line, to reinforce a cut that was made in the deck back in November.  Hem rebuilt both engines and ran each of them, but port still needs more work so he took the head off to work on it.  Hem also gave Jon the rebuilt port lower gear‑cluster so Jon installed it and refilled the leg with oil.  Houa finished the rail he's been making to go around the battery area and epoxied it in.  Max trimmed and epoxied down several complicated sheets of foam, and started working on a cute little hatch for our new compartment.  Starboard fo'c's'l was sanded and prepped for gelcoating, but port fo'c's'l has some rotten wood that needs to be replaced.  The area behind the cockpit seat finally got foamed, and 11 areas where bolts go through were de‑cored and filled with glass strips.  Our boom, forebeam, rudders, and anchor platform were taken to Luck Engineering for welding work, and Luck sent a stainless steel guy to start our hand‑rails (2 each side), and swim ladders.  Two joint‑lines on the targa bar were opened up, filled with epoxy mud, and glassed over.

Max fitting his complicated bit of foam to the port foredeck
Max fitting his complicated bit of foam to the port foredeck

Week 30, May 14 - 20, 2012:
Max got the entire foredeck foamed in, laying several complicated sheets of foam.  Sue cleaned almost 100 de‑cored holes, then Lek and Kao filled them with epoxy mud and glassed them over.  The back of the targa bar was ground back and reglassed, but some of the glass didn't setup and had to be removed.  Jon epoxied plates into each bathroom to hold our new mixing‑valves.  Houa made good progress on his long foam sheet to replace the shelf in the port fo'c's'l.  Mee trimmed down 8 sheets of foam to raise our swim platforms, and glassed one side of each of them.  Our boom, forebeam, and anchor platform came back from the welder and were stripped of paint, but now we're not sure if we want to repaint them.  Finally, Hem got our port engine put back together and tested.  And we celebrated our 33rd anniversary at a lovely restaurant on the water, well away from the boatyard!

New foam raising the floor of the starboard swim platform
New foam raising the floor of the starboard swim platform

Week 31, May 21 - 27, 2012:
Our main goal now is to glass in all exposed foam before we leave for the US next week.  We had a lot of rain this week, but still made good progress.  Max managed to glass in most of his exposed foam up in front of the salon.  Kao and Max also (finally) glassed in the back of the cockpit seat and the aft‑deck.  This foam has been exposed for so long that we were getting a bit worried about it, but it seems OK.  The old grab‑rail troughs were ground back and prepped to be filled, and the shelf for the port fo'c's'l got more glass.  Both swim platforms were raised by a good 3" (7.5cm) using 4 sheets of glass‑wrapped foam.  Our machine shop finished our sinks, rudders, and autopilot reduction gear.  They also delivered our swim ladders - they're just tacked together for now, but the shape and hinges look excellent, so grooves were cut in the swim platform floors to hold the ladders when they're up.  Finally, the battery box got a final coat of gelcoat so Jon moved the batteries back into it, and we found a prod we can use to fly some light‑air sails from.  A good week!

Port side grab-rail, above the windows
Port side grab-rail, above the windows

Week 32, May 28 - 31, 2012:
A short week as we flew back to the US on Thursday, so much of our work was preparing Ocelot for being left alone for a couple of months.  Houa put our sliding entryway door back together so we can close Ocelot up.  Lots of tools and gear was moved to the workshop - then we suddenly got a message that we had to move everything out of the workshop and into a new storage location, which produced a mad panic.  Jon drilled out all of the holes that had been de‑cored earlier, and then drilled out drains for our 2 new compartments up forward.  Luck engineering tacked together the new grab‑rails for the sides of the main cabin and added 2 additional supports to the backrest for the cockpit seat.  Finally, Jon reassembled the batteries in their new compartment, cleaning, greasing and servicing all the connections and then strapping the batteries down to their fancy new rails.


Break while Jon and Sue fly home for Amanda's Graduation, June 1 - August 5, 2012


Houa trimming the port transom & the channels for swim ladder
Houa trimming the port transom & the channels for swim ladder

Week 40, August 6 - 12, 2012:
A bit slow this week as we're still gearing up.  Jon repaired a couple bubbles in the fridge fiberglass and then started the fridge so we can have cold drinks.  He also shredded the skin on his hands raising the back of our huge tent so we can start work on our new rigid bimini.  The instrument console at the helm was cleaned up and reattached.  We removed our headstay and disassembled our jib roller gear so it could be cleaned and checked.  Houa worked on the backs of the transoms, grinding out the channels where the swim ladders will hang when they're down and filling in the rest of the transoms with foam and epoxy mud.  He also rounded the corners of the grooves for the swim ladders and glassed in the port-side grooves.  We used our new laser to determine how much to jack up Ocelot's bows to get her level again, so we can paint on the new waterlines correctly.  Amanda recorded many of Ocelot's dimensions and created a solid model so we can play with different options for our bimini and the steps going down to the swim platforms.  Jon removed the old, broken wiring conduits from the mast in preparation for putting in new conduits.  Golf and Kao filled the old grab‑rail troughs with foam and glassed them over.  They also put another 2 layers of glass on the aft‑deck to strengthen it.

Houa about to shape the new foam on the starboard wall
Houa about to shape the new foam on the starboard wall

Week 41, August 13 - 19, 2012:
A good week!  We still need more workers but we're making progress.  Our good friends from Vamp arrived and Kim spent several days helping us with our mast wiring and offering us the benefits of his considerable boat building experience.  For the mast we bought the extra tinned wire we need as well as several lengths of PVC conduit to hold the mast wiring.  The PVC was slit to go up the internal mast tracks, and diamonds were cut out of it to go around the bolts which protrude into the track for the conduit going to the masthead.  Cruising friends have offered us their scooter, so we retrieved it from Yacht Haven at the top of Phuket Island.  This will make it much easier to nip out quickly for tools and supplies.  Sue and Golf bought some more foam and epoxy so we have the immediate supplies we need.  The swim ladder grooves were glassed in and the swim ladder mounting areas were routed out and filled with solid fiberglass.  The walls coming down to the swim platforms had foam sheets epoxied to their tops so they come down at the ends of the swim platforms.  Our new worker, Mee, removed a plywood backing plate from inside the targa bar and replaced it with solid fiberglass.  Then he cut out the shelves to go above our forward port‑lights - our "eyebrows" - and glass wrapped both the supports and the shelves themselves.  We had a good discussion with Golf about money and the future of the project, so we're feeling cautiously optimistic.

Golf & Houa try an interesting variant on curved steps
Golf & Houa try an interesting variant on curved steps

Week 42, August 20 - 26, 2012:
A productive week, despite lots of rain!  The biggest gain was that the steps inside the sugar‑scoops were started - the step positions were laid out, the steps were designed, the foam was cut and shaped and then fiberglassed.  The mast continued to get polished, and we arranged all the halyards where we want them.  Both walls down to the swim platforms were raised and faired so they come down to the swim platforms correctly.  The mounting areas for the swim ladders were routed out.  Amanda measured up much of Ocelot so she could model some of our additions, like the sugar‑scoop steps and the new bimini, in her 3‑D modeling program, Sketchup.  Mee made progress on the foredeck area, creating gutters for those new hatches.  We used our laser to get Ocelot level, so we can mark out where our waterline is to go (an extremely frustrating project due to Ocelot's asymmetry).  Finally, we started on the bimini project, cutting out 5 frames to shape the bimini foam correctly.

Our finished bimini mold!
Our finished bimini mold!

Week 43, August 27 - September 2, 2012:
We got rain for the first few days but then glorious sunshine and we accomplished a lot.  Kao and Jeng cleaned the storage lockers under the cockpit.  Both engine hatches were ground back and prepared to receive foam stiffening sheets.  The hollow on the outside of the port sugar‑scoop was filled with a light fairing compound.  On the bimini project, we cut off the old bimini support bars.  While we were at it, we extended the backs of those bars to extend our davits by 7" (18cm) so the dinghy comes up more smoothly.  Once the rain stopped we cut 5 forms for the bimini shape we want and assembled them into a good, strong frame.  Then we bought 6 sheets of foam and laid them up in 2 large layers, with glass on only 1 side.  These will be bonded together to become the new bimini.  On the sugar‑scoop steps, small shelves were installed around the inside of the port sugar‑scoop and the 2 steps were epoxied onto them.  Then the edges were fileted and glassed.  The upper starboard step had to be taken apart and reassembled, as it was originally built as an exact copy of port, not a mirror image.  Then it was trimmed down until it matched the port steps.  Mee installed some cute gutters around the starboard forward hatch, but he kept getting pulled off that project to help elsewhere.

Flipping over a large, wet, sticky, floppy sheet of foam
Flipping over a large, wet, sticky, floppy sheet of foam

Week 44, September 3 - 9, 2012:
A good week!  On the bimini, we mounted one foam panel to our wooden frame/mold, leveled the mold, slit the front of the second foam panel so it would bend, and epoxied the second foam panel on top of the first, using tie‑wraps (cable‑ties) and weights to hold the 2 panels together.  Then we trimmed up the edges and put on the first of 4 reinforcing rails, this one across the front.  Golf's team got the shelves for the starboard sugar‑scoop steps mounted and then installed the steps themselves, fileting the edges and glassing them in.  Then they turned their attention to the cockpit, where they glassed in some small bits of exposed foam before starting to rebuild the rims around the teak decks.  Golf started on the targa‑bar, applying gelcoat and filler and then long‑boarding it until it's smooth.  Houa foamed and glassed both of our engine room hatches, which are much stiffer now.  Jon and Amanda measured out where the reinforcing pads for the sugar‑scoop rails need to go and then drilled out 3" (8cm) holes, which Sue then started filling with epoxy and fiberglass.  They also determined where the pad‑eyes for the prod need to go in the bows, and Jon ground out the port side so Sue could start filling it with epoxy and glass reinforcing.

Golf spraying a primer coat of gelcoat on the targa-bar
Golf spraying a primer coat of gelcoat on the targa-bar

Week 45, September 10 - 16, 2012:
Most of the activity this week centered on Ocelot's cockpit (for Golf's crew) and on our new bimini (for Team Hacking).  On the bimini, we built up the back where it's going to bolt onto the targa‑bar with fiberglass, and we added 3 strengthening ribs - one on each side and one in the middle.  These were built up with thin glass strips between each layer of foam (which required lots of cleanup with sanding grinders), carefully shaped so they look nice and are easy to grab, and then were covered with 2 thick layers of biaxial glass.  Sue also filled in 9 reinforcing points where we have to bolt into the hulls - 8 for the grab‑rails to go on top of the sugar‑scoop walls and 1 for the portside prod pad‑eye up forward.  Above the cockpit, the top of the targa‑bar was sanded and sprayed with gelcoat.  In the cockpit itself, the process of preparing for the new teak was started.  The borders where the teak will go were built back up with thin glass strips and then gelcoat.  This process has a ways to go.  This was a short week - on Saturday Amanda's university buddies Liz and Monica flew in so we spent the weekend showing them around Phuket.

Poor bimini - all the holes where we injected epoxy
Poor bimini - all the holes where we injected epoxy

Week 46, September 17 - 23, 2012:
The top of the targa‑bar got polished in preparation for the new bimini.  The cockpit also got some gelcoat work, to prepare it for the new teak.  The bimini got popped off its mold for the first time, but we were concerned about its stiffness, so we drilled about 100 tiny 2mm holes through to the joint between the foam layers and injected almost 3 liters of epoxy into that joint.  We put some filler on the front edge, which was long‑boarded and shaped and then the front was glassed in.  We laid a sheet of glass over the top on the starboard side, but ran out of epoxy to do the port side.  Houa ground out the many screw holes in Ocelot's flanks and filled them with epoxy mud before putting a glass patch over them.  Both port and starboard sugar‑scoops got 3 layers of biaxial glass laid over their walls, the last sheet going all the way under the transoms.  The steps also got a final layer of fiberglass to join them together.  Port side was cut back and shaped to match starboard and then the cuts were glassed over and a final sheet of structural glass was wrapped over the swim‑platform and under the transom.  Finally, we cut away the shelf at the very front of the starboard fo'c's'l to allow access to where the pad‑eye for our new prod will go.  We cut out the inner skin of glass and ground out the foam and old gelcoat so the area is now ready to be reinforced to handle the loads that pad‑eye will see.

Baw checking the fit on a hatch riser after cutting out the holes
Baw checking the fit on a hatch riser after cutting out the holes

Week 47, September 24 - 30, 2012:
A week plagued with bad weather and Golf being out with a head cold, but we still made some progress.  We laid a sheet of glass on top of the port side of the bimini and tested it for strength, but that was about all we could do on the bimini.  Since we've been building the bimini under our neighbor's boat and they're coming back next week, we moved our bimini work area to under Ocelot.  Baw and Houa finished glassing the starboard sugar‑scoop, thereby finishing the structural work on the sugar‑scoops.  Baw tried patching some of the many screw‑holes in Ocelot's flanks but had problems with the epoxy not curing, and many patches had to be ripped out, some of them twice.  Sue did a bit of glassing on the pad‑eye mounts for the prod up in the very bows, but she was worried that the moisture in the air would also affect her epoxy.  Houa cut back the mounting area for the swim‑ladders and then glassed over his cuts, so the ladders will mount flush with the swim‑platform.  Jon discovered some new, softer polishing pads and spent a lot of time removing corrosion pits and grinder marks in polishing the mast.  Sue found some left over paint stripper and used it to take the remainder of the paint off the mast, in those fiddly places that the grinders couldn't reach.  The big news is that Houa and Baw started working on the hatches, cutting the openings and preparing the new foam risers that the hatches will sit on.  They also outlined where the new, larger hatches will go in the forward cabins.  Finally, Golf and Jon met with Num, the new Yard Manager, to work out how business will be conducted at Coconuts in the future.

Jon testing the flex of the new bimini - Nice & strong now!
Jon testing the flex of the new bimini - Nice & strong now!

Week 48, October 1 - 7, 2012:
Work this week focused on the bimini and the foam frames that the 12 deck hatches will sit on.  On the bimini, we cut away the foam and glass at the back on the underside, where it will bolt to the targa bar.  Then Jon carefully ground a nice taper into the foam so there'd be no discontinuity that might create a stress concentration.  We covered the whole underside in a 2nd layer of biaxial glass and then laid 3 strips of glass across the back bolt surface in increasing widths.  The whole bimini seems much stronger now so we hope we're finished with the structural glass.  On the hatch frames, Baw and Houa carefully epoxied them down to the deck.  Then they punched out the foam where the bolts will go and filled those areas with reinforced "hairy" epoxy mud.  Four of the 5 hatch frames on starboard side have been glassed in with 3 layers of "UD" glass, and all 5 frames on port side are prepped and ready to glass.  We took 2 lengths of anchor chain and 1 anchor to our metal fabricator to be regalvanized.  Sue worked hard cleaning up the hatches themselves and Jon spent his idle time polishing the mast, a job that will continue for some time.

Removing port forward hatch cutout, with old hatch cutout (white)
Removing port forward hatch cutout, with old hatch cutout (white)

Week 49, October 8 - 14, 2012:
A rather slow week that centered mostly on the new hatches over our forward cabins.  The hatch locations were laid out and the deck cut away, then the foam hatch rims were constructed and epoxied down.  The foam where the bolts will go, and the foam below the rims in the deck, was dug out and filled with reinforced epoxy mud, but the rims themselves still need to be glassed in.  Sue continued refurbishing the hatches but having to get a root canal on Tuesday slowed her down.  In the evenings Sue worked hard to document all the finances of the refit, what quotes we've received from Golf, what they cover, what payments we've made and what they were supposed to cover, etc.  Jon helped Baw and Houa glass in the remaining hatch rims on port side and then sanded the glass down to allow the hatches to fit nicely.  Otherwise Jon spent most of his time polishing the mast.  We worked out that a new scrubby pad will clean the mottling off the mast, leaving it ready for the Nyalic.  We spent quite a lot of time in meetings, first with Golf and Houa to determine how much more time it will take to finish the work on Ocelot (56 man weeks!) and then going over Sue's financial report with Golf, and finally with the yard management to clear up some issues.  On Friday evening Amanda returned from a month of gallivanting around Thailand with Liz and Monica so we took Saturday off to drive around to the new Krabi marina.

Baw, Amanda, Jon & Houa hoisting the bimini up
Baw, Amanda, Jon & Houa hoisting the bimini up

Week 50, October 15 - 21, 2012:
Bit of a short week with holidays, the Vegetarian Festival, financial meetings with Golf, and Amanda having to make a visa run, but we made a deal with Baw and Houa that if they finished all the foredeck work (including the fo'c's'ls) by 2 November then we'd give them a $330 bonus, and this has energized them considerably.  We hoisted the bimini up and set it in place so we could see how it fit and start planning the forward supports.  We also glassed split PVC pipe to 3 sides of the bimini to act as bolt‑rope holders for side‑shades and the dodger.  Baw and Houa finished glassing in the last 2 hatch rims and then started on the foredeck, laying a decorative strip of foam on each side just at deck level and filling in the slight dish in both bows with epoxy fairing compound.  Houa shrank the access hole above the new tank area on port so the hatch will clear the shelf that will go above it, and Baw started building the hatch, glassing over a foam mold (some of the foam will be removed later).  We spent all of Friday moving all our junk from Manoon's land to a small apartment we've rented right next to the boatyard.  Golf got us some stainless steel plates to reinforce the new pad‑eyes, and Jon started cleaning up the edges.

Baw's hatch and frame, almost ready to be epoxied in place
Baw's hatch and frame, almost ready to be epoxied in place

Week 51, October 22 - 28, 2012:
We spent 1.5 days helping our neighbors get their mast stepped, lost a couple of worker days to illness, dental work, and the Vegetarian Festival, but we still accomplished some good stuff on Ocelot.  The strips of trim foam on each side of the main cabin got shaped and glassed in.  Houa filled and flattened the decks of both bows and epoxied on their final 2 layers of glass.  Baw finished and installed the port hatch‑frame over our new tank area, as well as the port hatch itself.  He also finished most of the starboard hatch gutters and modified Max's old hatch so it will work.  Amanda spent many hours preparing the stainless steel backing plates for prod's pad‑eyes, before we finished reinforcing the hulls where the pad‑eyes will mount and then epoxied the backing plates in place.  We found where the prod will go and marked the best angle for the pad‑eyes, and we drilled and tapped the mounting holes for the portside pad‑eye.  Once we finished, we gave Houa the go‑ahead to install the shelf in the port fo'c's'l, which got epoxied down but still needs to be glassed in.  Sue spent a lot of time cleaning up our hatches and Jon spent his idle time polishing the mast.

After sanding, a 2nd layer of gelcoat is applied over the filler
After sanding, a 2nd layer of gelcoat is applied over the filler

Week 52, October 29 - November 4, 2012:
This week Baw and Houa were supposed to finish all of the foredeck work by Friday if they were to collect their $330 bonus.  This included leveling and glassing the tops of both bows, installing the shelf in the port fo'c's'l, repairing the shelf in the starboard fo'c's'l, building both hatches and the supports for those hatches in front of the salon ports, gelcoating the area around the salon ports, and installing and glassing in the steps just above the salon ports.  They made a good try but couldn't finish the gelcoat or the steps, so after a long meeting on Saturday evening we ended up giving them half the bonus we'd talked about.  Jon finished drilling and tapping the holes for the starboard pad‑eye for the prod early (to clear the way for the fo'c's'l work) then moved on to preparing the bimini for gelcoat by sanding the entire outer surface.  He also laid out and drilled the mounting holes in the back of the bimini and bought the hinges and finger‑pulls for the hatches.  Amanda polished up much of the starboard side of the mast (the side currently facing up) and the women sanded a section to prepare it for the Nyalic.  Rachel and Sue cleaned up most of Ocelot's woodwork (doors, etc) at our storage unit, and Sue cleaned up many of the deck hatches to prepare them to get new acrylic and new gaskets.

Baw sanding new gelcoat in front of the unglassed starboard shelf
Baw sanding new gelcoat in front of the unglassed starboard shelf

Week 53, November 5 - November 11, 2012:
The big accomplishment this week was that Houa glassed in the 2 shelves above the forward salon ports.  To do this, Baw first had to finish the gelcoat work under the shelves, in front of the ports.  Baw also finished the gelcoat work on top of the targa‑bar and put gelcoat filler around that foredeck area and the underside of the bimini and started sanding it smooth.  One of those forward ports had to go to the machine shop to get the bolts removed, as they were solidly stuck.  Houa spent much of the week sanding the edge of the deck, cleaning up where it joins the toe‑rail and making sure the deck is flat.  Houa also cut out and trimmed down all 12 sheets of acrylic for our hatches.  Amanda accomplished a lot of polishing on the mast, and even more on the boom - only one of the 4 sides of the boom still needs polishing.  And on the mast we did a finish sanding and applied our first layer of Nyalic on a test‑section just above the first spreader.  The hinges and finger‑pulls for the 2 new hatches were laid out, drilled and de‑cored, and Houa filled them with epoxy mud so they can be tapped.  Jon replaced a broken davit block and mounted it to its stainless steel plate.  Sue and Rachel organized and inventoried much of the gear on Ocelot and moved several items to the storage unit.  Finally, Barak Obama won the US Presidential election (to much relief here) and Amanda got scooter driving lessons and now there's no stopping her.

Drilling & tapping mounting holes for the main-sheet track
Drilling & tapping mounting holes for the main-sheet track

Week 54, November 12 - November 18, 2012:
A slow week, as Houa couldn't work on Monday and Friday, and Baw quit the team on Tuesday (we eventually found that Golf hadn't paid him).  Our Nyalic test worked well, but then Amanda went off gallivanting around Cambodia with a friend.  Baw spread a bit of gelcoat on the cabin‑top, but later we found this is not the good quality isophthalic gelcoat that we'd paid for.  Golf had taken our $1,000 but only bought cheap gelcoat, and presumably pocketed the difference.  Houa made good progress in the galley, building the front facade and lowest shelf for the sink cabinet.  Jon mounted the hinges and finger‑pulls on the 2 forward hatches in front of the main cabin, and trimmed the edges of the hatches down so they clear the water‑catching gutters under them.  Jon also worked on the targa‑bar, finding the center‑line, putting the solar panels back, mounting 3 sets of blocks and their mounting plates, and drilling and tapping all of the mounting holes for the main‑sheet track.  Sue sanded another section of the mast, so it's almost ready for Nyalic, but she also put in a huge amount of work on a big spreadsheet of our costs for this refit.  From this we were able to determine very accurately how much Golf has spent on Ocelot - about $30,000 or roughly half of what we've paid him.  We had some long conversations with Golf about what has happened with the rest of our money but we're not sure he really understands what will happen if he fails us, or how successful he'll be if he makes us happy.

Rolling the epoxy into the 2 glass strips under the port hull
Rolling the epoxy into the 2 glass strips under the port hull

Week 55, November 19 - November 25, 2012:
Bit of a slow week as Golf never showed up, Baw only worked 2½ days because Golf didn't pay him, and Houa had commitments on our neighbor's boat for a few days.  Our big accomplishment was laying 2 strips of biaxial glass down the entire length of both hulls, to bond the joint‑lines from the outside.  To do this, Jon had to grind off the old antifouling and gelcoat from 4 places where supports had been placed to make sure Ocelot didn't fall over (Ocelot sits happily on her keels and needs no other support).  Jon also sanded many other areas of the hull to smooth them down a bit, and he spent more time polishing the mast.  Sue did a lot of sanding and paint stripping on the mast and was able to apply Nyalic to finish the area between the first and second spreaders.  Jon drilled the holes for the deck‑fills for our new forward tanks and de‑cored them so Houa could fill in where the balsa was with epoxy mud.  Houa worked all week on the sink cabinet in the galley, which is more complicated than any of us realized.  Baw spread gelcoat filler and sanded it smooth on the underside of the bimini.  Thursday was our Thanksgiving and Sue prepared a sumptuous feast (with only a microwave) which we shared with our Aussi neighbors.  We talked to another contractor to get prices for finishing the antiskid and gelcoat on the decks, since Golf isn't answering his phone.

A frenzy of activity all over Ocelot's decks
A frenzy of activity all over Ocelot's decks

Week 56, November 26 - December 2, 2012:
The week started off slowly but really took off at the end, with the arrival of several more workers.  The big news is that we met with Golf and got him to sign a letter of what payments we'd made to him.  We also gave him a copy of our graph that shows what has been spent on Ocelot - about half of what we've given him.  After ripping us off like that, he had the gall to ask us to pay him for his time, even though he couldn't explain where $30,000 of our money went.  Houa spent the week working on the galley sink cabinet - apparently it's much more complicated than we thought.  Baw worked on the bimini, removing a bad bump and smoothing the whole surface with gelcoat filler.  Jon continued polishing our spars and also ground out and glassed up some whale damage from 2007.  We celebrated Loy Krathong by helping launch our neighbors and good friends, and setting our little offering adrift.  Sue dug out the hinges and latches for our deck hatches and started cleaning them - several will need to go the our stainless worker for some welding.  Sue also spent time cleaning up the toe‑rails, although we're not sure what we're going to do with them.  E‑U's team of 3 workers started on Friday and immediately started sanding the deck and applying gelcoat filler to smooth it out.  Mike and Wiwat came to tell them what's needed.  We cut some sections of large PVC pipe to use as sanding forms, so we get a consistent radius on the transitions from cabin to deck.  But a batch of gelcoat on Friday didn't harden so all of Saturday (and Monday and Tuesday) was taken up with trying to remove it from 3 areas, an ugly job.  We chose our color for the deck (a warm off‑white, now dubbed Ocelot White) and sent the color sample to the gelcoat manufacturers, but Jon realized that the targa‑bar will have to be re‑sprayed so he started removing all the hardware he'd mounted up there.  We also started looking at teak decks to see how we want our cockpit rebuilt.

Removing gelcoat goo with acetone and wire brushes
Removing gelcoat goo with acetone and wire brushes

Week 57, December 3 - December 9, 2012:
The week started off by continuing to clean off the gelcoat goo that didn't harden from Friday, an ugly job that continued through Tuesday.  Our friends on Vamp gave us a hand on Monday, which was very appreciated, but then the anchorage got rough and they left.  Houa finished assembling the galley sink cabinet but it still needs trim and finish work.  Amanda came back from Cambodia but she seems to have picked up some sort of low grade bug and couldn't help much.  Most of the work was laying down more polyester filler and sanding it smooth.  Putting the correct radius on the corners, like around the hatches or where the cabin meets the deck, takes a lot of time and patience, but it's difficult to tell these guys that the decks are already very flat and they only need a tiny amount of filler.  Baw finished wet‑sanding the bimini to 240 grit and will now move up to the deck as he understands what we want.  The bimini is looking very nice and is now ready to be sprayed with its final coats of gelcoat.  Sue spent a lot of time sanding the toe‑rail and is almost finished with it.  She also delivered our headsail to Rolly Tasker for cleaning and picked up our new $1,000 headstay as well as our old headliners (which still need work).  When Jon wasn't running out to get supplies for the guys he was polishing our new prod, which was in terrible shape, or hunting for better quality electrons and building a heavy duty cord to reach them.  Our stainless steel workers from Luck Engineering came and fitted our new grab‑rails along the sides of the main cabin and the reinforced backrest for the cockpit seat.  They fit perfectly and look gorgeous, but their rails for the sugar‑scoop walls didn't have the pads in the correct places so they'll need to be reworked - a shame because they're all polished up and look beautiful.  Mike from Wiwat came by on Saturday and noted that the workers are creating work for themselves so we feel better directing them more firmly.

Lek & Baw use a bendy rod to see how much filler will be needed
Lek & Baw use a bendy rod to see how much filler will be needed

Week 58, December 10 - December 16, 2012:
A pretty good week!  We had 6 workers from E‑U's team plus Baw and Houa working pretty much all week.  First job was to sand areas of rough fiberglass, then any areas that weren't flat got polyester filler and were sanded flat and smooth.  Nut made excellent progress on the many complex surfaces around the entryway.  Bank put a ton of time into trying to make our aft cockpit wall smooth and flat, but it's not there yet.  Baw has taken over as one of our team leaders (the other is Chai) and seems to have taken a personal interest in making sure Ocelot is done as well as possible, which is certainly gratifying to see.  He spent most of his time on the port sugar‑scoop, filling, fairing, sanding, and checking.  The outer wall has a big hollow in it which needed a lot of filling and still needs a lot of sanding.  Chai is nominal team leader for E‑U's workers but he spent most of his time on the starboard sugar‑scoop, making good progress.  Song worked up on the foredeck, which is a big job given all the complex curves up there.  Pooton worked under Ocelot, sanding back the bad gelcoat on the helm seat and then going after the louvers for our side windows.  Sue spent much of the week sanding the mast and cleaning up deck hardware - hinges, latches, pad‑eyes, etc - and checking what needs to be repaired, but she also sanded the grooves for the swim ladders.  She even got some more of the mast coated in Nyalic.  Jon hooked up a new high‑capacity electrical line so the tools get better voltage, and rewired the power input to Ocelot so we get simultaneous 110v and 220v power, removed the solar panels from the targa‑bar, put up awnings on 3 sides of our tent so we get more shade to work in, removed some stuck hardware from the helm seat, and he bought 2 new sanders so we don't have to pay the high rates (7%/day!) to rent them from the yard.  Houa essentially finished his work in the galley, finalizing the sink and its trim, building and mounting a new drawer, and fitting new hinges for our rubbish bin.  Mike from AME Marine came by to discuss progress and took our hatches off to be powder‑coated.  Amanda was our polishing queen, working long hours with mask and grinder on the aluminum spars -- the prod, forebeam and mast.  She also worked up computer graphics for several versions of teak for the cockpit.

Jon using our laser to mark out our antifouling paint line
Jon using our laser to mark out our antifouling paint line

Week 59, December 17 - December 23, 2012:
It was a week of attacking some big areas that need lots of work.  Baw and Lek spent most of the week on the port sugar‑scoop, which needs the most attention, while Chai worked on the starboard sugar‑scoop.  Both needed a lot of fairing of the outside walls to blend them into Ocelot's hulls.  Luk's men came and told us to mount the pads for the stern rails, and then the walls could be finished.  When the walls are finished, they'll come back to weld up the rails in situ.  Nut worked on the many walls around the entryway, an area that was completely rebuilt so needs a lot of cosmetic work.  Bank struggled with the aft cockpit seat but hasn't made much progress.  Song started the week working on the foredeck but couldn't take direction so he has left the team.  We've been promised 2 replacements but they haven't shown up yet.  Houa finished his work in the galley and moved to other salon projects, replacing: some floor supports, the top step to the starboard hull, the access door for a salon storage area, and the teak board under our front window.  Houa also sliced a slot into the bolt‑rope holders on 3 sides of the bimini.  The slots were then sanded smooth and the bimini was moved out in front of Ocelot so some soft gelcoat could be removed.  The holes in the cabin‑top where the bimini supports used to come down were filled, glassed, sanded, and covered in filler.  The 2 diesel and 2 water fill holes were drilled out and sealed with epoxy.  Sue continued working on many small projects, overseeing the team, photography, and the projects finances.  Jon used our laser to draw in the antifouling paint line on both sides of both sugar‑scoops so the polyester filler could be removed below that line.  Amanda continued polishing our spars, and finished our new prod.  We threw the workers a beer and chips party Saturday afternoon, and gave Baw a raise because of his dedication to Ocelot's rebuilding.

Baw spraying gelcoat on the outside of the port sugar-scoop
Baw spraying gelcoat on the outside of the port sugar-scoop

Week 60, December 24 - December 30, 2012:
A short week for us as we took almost 2 days off for Christmas with our friends on s/v Vamp, but the guys (mostly Muslim) worked all week.  Baw masked most of the foredeck and sprayed Thai gelcoat over many areas, to make sure surfaces were appropriately finished.  Houa made excellent progress, finishing several floor supports and the top step to the starboard hull and most of the headliners for the bathrooms.  Jon seemed to spend most of the week on the scooter, running errands and shopping for boat bits.  We got 2 new workers - Jack worked under Ocelot, finishing the top of the bimini and also sanding many small bits - hatches, access panels, louvers and such.  Yoong finished filling and sanding the targa bar to prepare it for gelcoating next week and moved on to the cockpit.  Baw and Lek wet‑sanded the port sugar‑scoop to a nice shape and finish.  Chai continued with the starboard sugar‑scoop.  He's a little behind Baw so has to match Baw's shape.  Nut and Bank spent most of their time sanding the fiddly bits on the main cabin.  Sue played Project Manager, carefully running herd on all the action.  Max visited and was awarded one of our new Ocelot Refit Team T‑shirts.

Lee and Mike spraying gelcoat on the targa-bar
Lee and Mike spraying gelcoat on the targa-bar

Week 61, December 31, 2012 - January 6, 2013:
A long week for us, as we worked all 7 days, including New Years.  Our big accomplishment was that the targa‑bar was stripped, prepped, masked, and sprayed with 2 coats of our "Ocelot White" gelcoat by Mike and his AME team!  The bimini was also prepped and 2 coats of gelcoat were shot onto the underside.  The top of the bimini got some gelcoat but a compressor malfunction prevented finishing it.  We only had a full set of workers on Thursday and Friday, and no workers at all on Monday, Tuesday, or Sunday, which let us get 2 full coats of Nyalic on the starboard side of the mast.  Jon hauled out a huge tarp from the workshop, taped over its holes, attached it to a long PVC pipe, and attached it along the starboard side of our tent so it could be raised and lowered when necessary.  Sue finger‑sanded the starboard deck to fair the Thai gelcoat into the surrounding fiberglass.  Houa made excellent progress in the heads, ripping out the old rotten wood and building replacements in plastic‑board, which should get installed next week.  Two men from Luck Engineering arrived and finished tacking together the railing for the starboard grab‑rail.  Many of our removable hatches, louvers, etc were prepped for final gelcoat while the AME team was spraying.  Many of the vertical walls in the cockpit were also sanded to prepare them for gelcoating, and the starboard sugar‑scoop got more filler to improve its shape.  Amanda spent several hours in her bunny‑suit, smoothing several patches of fiberglass on Ocelot's hulls.

Mike and Deng spray final gelcoat layers on the bimini top
Mike and Deng spray final gelcoat layers on the bimini top

Week 62, January 7 - January 13, 2013:
We noticed a wonderful change in the yard's attitude towards us this week - they actually seem to like us.  Mannop spent hours repairing our compressor (he's quite a mechanical magician) and wouldn't accept any payment beyond parts.  Hope the attitude lasts!  Cris called our whole team together for a meeting on Monday and translated everything so everyone's on the same page.  On the bimini, the men sanded and filled the top and the AME team came to finish spraying the gutters and edges with gelcoat.  Then our guys flipped it over and started wet‑sanding the bottom, starting with 400 grit.  Jack and Chai spent most of the week filling and sanding smaller panels, hatches, and louvers in the newly expanded workshop, getting several ready for spraying with gelcoat.  Baw led a team filling and sanding the starboard sugar‑scoop and then masking and spraying it with our ISO 2500 gelcoat.  While he was spraying, he also sprayed 5 smaller hatches and covers that had been finished.  The team from Luck Engineering finished completely rebuilding both of our aft grab‑rails.  Houa fitted the headliners and 2 plastic‑wood boards in each starboard head.  He finished shaping the other 3 pieces for those heads, but wants to paint them before installing them.  Then he moved over to portside and cleaned it to begin his work there.  Sue and Amanda got TMT, who made our tent, to do all of our headliners for us, a big job.  Jon ran a test on the mast wiring conduit to determine the force needed to force it up the mast - 286kg or 630 lbs.  Several folks worked on the vertical surfaces in the cockpit.  They also finished most of the surround for the teak on the aft‑deck.

Middle of shoot - tape on near side has disappeared under gelcoat
Middle of shoot - tape on near side has disappeared under gelcoat

Week 63, January 14 - January 20, 2013:
Two big accomplishments this week: First, the underside of the bimini was sanded to 2000 grit and polished, giving it a mirror-smooth reflective finish.  Second, the team prepared the cabin‑top and Mike sprayed all the areas outside of where the nonskid will go (the "gutters") with gelcoat.  This involved applying more durable masking to the windows and filling all 100 mounting holes with epoxy, de‑coring the 22 holes that still needed it.  The team from Luck reworked the sugar‑scoop grab‑rails so they fit better, then took them off for final polishing.  Houa was pulled off the bathrooms and put onto making new plywood for the headliners, to replace the water‑damaged ones.  These were then epoxy coated.  Lots of work in the cockpit, and Jon remounted the starboard side aft cockpit door, as well as de‑coring the area around the emergency steering bearings and the engine room hatch pulls.  Several other small epoxy jobs got done, including filling the holes in the starboard chain‑locker and in the bottom of the life‑raft locker and where the backrest bolts to the aft cockpit seat.  Jack kept sanding the hatches and the cockpit seat, preparing them for gelcoating.

Mike spraying the foredeck inside a plastic tent of masking
Mike spraying the foredeck inside a plastic tent of masking

Week 64, January 21 - January 27, 2013:
The week started slowly but we ended up getting a lot done.  Nut spend several days sanding the underwater parts of the hulls (for which he received additional pay) removing the high spots so we don't have to use as much filler to fill the gouges left by the grinders that took off the gelcoat.  K worked with Houa all week.  They epoxied and sanded the headliner boards, then ripped out some wet plywood in the portside cabins.  Houa ripped out some rotten wood from the portside heads and started making plastic‑wood replacements.  Jon mounted and trimmed the portside aft cockpit door and disassembled our feathering Kiwi prop, finding a bent spring inside.  He drilled a pair of drain‑holes in the new hatch gutters up forward, so we can mount PVC drain‑pipes in them.  He also found how to modify West System epoxy pumps so they'll work with our Epotek epoxy!  Baw's team worked on the foredeck, directly in front of the salon, and on the targa‑bar, getting them ready to be sprayed with gelcoat.  Sue and Amanda kept a close eye on Baw's team, asking them to fill small defects they'd left behind.  Friday and Saturday were gelcoat spray days, as Mike and his team from AME sprayed the foredeck, the lower targa‑bar, several hatches and louvers, and touched up 2 areas of the bimini.  Our team did much of the masking, and provided support when they weren't sanding the sprayed bits.  Jack put tiny blobs of gelcoat on the pinholes that formed in the gelcoat, saving us an additional sanding step.

Baw and Jack smoothing out filler under the sugar-scoop
Baw and Jack smoothing out filler under the sugar-scoop

Week 65, January 28 - February 3, 2013:
The bad news this week is that we found that the epoxy filler on the outsides of our hulls and all along the waterline is very soft and porous.  Whether sun damaged or poorly mixed, it ALL has to come off before we can start re‑contuouring the hulls into nicely rounded shapes.  Lots of sanding that we weren't planning on.  But the rudder bearing project looks a bit easier than we'd thought, due to larger than expected rudder‑tubes.  Baw and Nut made excellent progress and finished preparing the port side‑deck for gelcoat, bagging it in plastic to preserve their work.  They also made good progress on the starboard deck, spreading filler on the hatch supports and sanding it smooth.  Houa and K worked on portside, creating plastic‑wood strips for the heads and removing the rubber and plywood kick‑boards in the cabins, replacing them with formica.  K cut his thigh and needed 7 stitches, our worst accident to date.  Jon found that West Epoxy pumps can be modified for our Epotek epoxy, which led to us applying phenolic‑epoxy mud to the starboard outside waterline.  Two more applications were required before we had a nice, smooth transition from topsides to hulls.  Sue and Amanda worked on polishing the spars and cleaning bits that need to be replaced.  They also bought some epoxy paint from another cruiser, but it turns out not to be appropriate for nautical work.  Jon repaired R2D2, our shop vac, and de‑cored our 2 water‑fill holes on deck.  The starboard topsides were long‑boarded (again) and some filler was spread into some low areas.  And we spent a wonderfully glorious Sunday out on the water, sailing to a neighboring island for some snorkeling.

Sanding off the remaining bad filler using big polishing motors
Sanding off the remaining bad filler using big polishing motors

Week 66, February 4 - February 10, 2013:
Lots more sanding and filling of the starboard topsides, but Baw mixed some of our new gelcoat with some filler and it didn't harden, so it ALL had to come off - a huge job that saw the yard contributing several power tools to us, all for free!  Now we're back to filling and fairing, making the topsides smooth and uniform.  The guys typically do 2 filling/fairing cycles a day.  Jon epoxied in the gutter drains for the 2 new forward hatches and filled where he'd de‑cored the water‑fill holes in the deck, and he also repaired a powerful grinder and a small palm sander that we can now call our own.  Baw shaped the starboard bow and then moved over to port, sanding away the old filler first.  We got the mast flipped over and Sue and Amanda started polishing the port side.  Our headliners came back from TMT and we talked with Doyle (China) about making us new sails.  Jon and Amanda started designing the pattern for the cockpit teak, and also removed the starboard cap‑shroud chain‑plate.  Our new worker, Duk, started sanding off the old epoxy filler from portside.  The inside waterline of starboard hull was sanded clean and smeared with 2 layers of phenolic epoxy filler.  Houa and K found problems with the steps up to the portside bunks so they did a lot of repair work, as well as making new bits of teak trim to go around the formica.

Spraying gelcoat on the starboard topsides - goodbye stripes!
Spraying gelcoat on the starboard topsides - goodbye stripes

Week 67, February 11 - February 17, 2013:
Both cap‑shroud chain‑plates were removed, along with their backing plates.  The silicone around them was cleaned up and then the 3 lower bolt‑holes in each were de‑cored before all of the holes were filled with epoxy mud.  Eight water/fuel vents were also de‑cored and filled with epoxy mud.  The starboard topsides were filled and faired smooth, then Jon and Amanda shot in a gelcoat line (above the waterline but below the paint line) with the laser.  Port topsides needed more work as it had more bad filler to remove as well as the old whale damage repair, then lots of filler was added to make it all smooth again.  The waterlines on the inside of starboard hull and the outside of port hull were sanded back and phenolic‑epoxy filler was screed on and sanded smooth.  Sue and Amanda put in a lot of time polishing the mast.  Houa and K worked on new bits of teak trim for the cabins, and new supports for the cabin floors.  The starboard topsides and the port side‑deck were completely masked off with heavy plastic so Mike and the AME team could spray gelcoat on the starboard topsides on Thursday, and the port side‑deck on Friday and Saturday.  The guys started sanding the starboard topsides with 320 grit and soapy water but after the gelcoat spraying was finished we put them to preparing port topsides for gelcoat.

Lining up the drill with strings to remove the lower rudder bearing
Lining up the drill with strings to remove the lower rudder bearing

Week 68, February 18 - February 24, 2013:
Most of the effort this week went into filling and long‑boarding the port topsides, getting them ready to be sprayed with gelcoat.  Sue, Baw and Nut put in a lot of time preparing the starboard side‑deck for gelcoat, filling areas that need it and sanding out little pin‑holes.  Sue and Amanda also put in a lot of time on the mast, and fetching supplies for the men.  The vertical walls near the entryway and behind the aft cockpit seat were sealed with epoxy (to prevent some blue paint from showing through) and then sanded rough to prepare them for gelcoat.  Jon repaired the charger for our battery‑drill and used a friend's sharpener to sharpen several of our drill bits.  Houa worked long hours alone, repairing much of the work that K had done badly (K won't be back).  Jon used string and a pair of tapered plugs to find the exact axis of our rudder shafts, and super‑glued strings to the hull as guides for drilling out our old rudder bearings.  The yard provided a big drill and with Sue and Amanda acting as spotters, telling Jon which way to point the drill, he drilled out both of our old rudder bearings and enough of our rudder‑tubes to accept our new rudder bearings. This job was much tougher than expected, taking the best part of 4 days.  The port inside waterline was sanded and filled with phenolic‑epoxy, and most of the guys started working on the bows, between the hulls, filling and fairing.  Jon and Amanda shot in the port gelcoat line with the laser, but Baw felt that port topsides needed more work.  It turned out that Mike was too ill to spray gelcoat so that was put off until next week.

Rudder taped with the taped bearing sitting on the shaft
Rudder taped with the taped bearing sitting on the shaft

Week 69, February 25 - March 3, 2013:
A good week as we made visible progress on several fronts despite Sue being out with a head cold for much of the week and Amanda having to fly to Penang to renew her visa.  The port topsides were filled and faired smooth, masked, scaffolded, and shot with 30 kg (66 lbs) of gelcoat, which was then completely wet‑sanded with 360 grit.  It needs some touch‑up re‑spray but it's looking nice.  Mike also gelcoated the nonskid gutters on the starboard side‑deck while the guys wet‑sanded the starboard topsides to 400.  The bulk of the prep‑work happened between the hulls and by the end of the week it had all been filled and faired smooth and the gelcoat line marked, with new filler around the emergency hatches and the trampoline holders.  The big news was that we got the new rudder bearings machined, aligned and epoxied in place, with release tape around them to facilitate removal.  Houa made good progress in the aft cabins, replacing some water‑damaged wood, remounting the headliner supports, building a new bed to repair the whale‑damaged one and extending both aft beds a few inches.  Jon completed several small jobs - a drain‑hole in the port topsides was found and opened up, 6 drain‑holes were de‑cored and filled, several tools were repaired, and much of the starboard gelcoat lip was faired.  Sue and Amanda put in lots of time polishing the mast, and Amanda chipped back some gelcoat that wasn't adhering correctly on the port sugar‑scoop.

P'Wat spraying the bows and the trampoline holders
P'Wat spraying the bows and the trampoline holders

Week 70, March 4 - March 10, 2013:
Baw wet‑sanded the forward half of the port topsides through 2000, and it's looking very nice.  But the aft half of port topsides needed to get rough sanded and re‑sprayed, as it was a bit translucent.  The starboard topsides were wet‑sanded up through 1000 and then all the many little pin‑holes were filled with dots of gelcoat.  The insides of the hulls and under the bridge‑deck were filled and faired and prepared for gelcoat.  The trampolines were dug out, suspended where they'll eventually go, and holes were drilled in the support tubes for the lashings.  The holes were then opened up into nicely rounded vertical slots, but we noticed that the rods that Golf put in there are too short.  Amanda found that she could chip off some of the gelcoat up on deck.  It obviously isn't adhering properly and will also have to be re‑sprayed.  We finished rough‑polishing the corrosion out of the port side of the mast and started polishing it.  Houa built the new bed for the port aft cabin, complete with opening hatches, and coated it all with epoxy.  Then he bought sheets of rubber and foam to build sound and thermal insulation to go under both aft bunks.  Our life‑rings were taken to Rolly Tasker to get recovered.  Unfortunately, Sue broke her wrist jumping off a drum and it will be in a cast for a month.  The good news is that Mike and P'Wat sprayed gelcoat on the port aft topsides as well as the entire area between the hulls!  The guys immediately started sanding the new gelcoat before it got too hard.  A hash‑pipe was found in our work area, and Jack and Chai were moved to other projects in the yard and we got 2 new workers, Beng and Nai.

Sanding (rock hard) gelcoat above your head is harder work!
Sanding (rock hard) gelcoat above your head is harder work!

Week 71, March 11 - March 17, 2013:
Most of the guys worked under the bridge‑deck all week, wet‑sanding the new gelcoat - a difficult job as they have to work over their heads.  Baw tried a pneumatic sander for a while until it blew a bearing.  Lek worked alone, sanding the aft half of port topsides, another area that was sprayed last week.  He got most of it to 400, so we want the dots filled before they go to finer grit paper.  Team Hacking made excellent progress on the mast (despite Sue's left arm being in a cast), getting the whole thing polished, most of it sanded to 600, and the top half (above the second spreader) sanded to 1000 and coated with Nyalic!  Houa worked in the aft cabins, repairing and epoxying in the bed in port (old whale damage), adding new access hatches under the bed, sticking on new sound insulation, enlarging an access panel so we can get to the fill‑pipes for the port diesel tank, and repairing the starboard engine access hatch.  Several side‑trips were necessary: Sue had to replace her initial cast with one more permanent, and she had to get her expiring passport replaced.  Jon spent a morning helping friends remove their masts, and on Sunday those friends hosted a wonderful BBQ/pool party.

Love the reflections in the polished gelcoat under the bridge-deck
Love the reflections in the polished gelcoat under the bridge-deck

Week 72, March 18 - March 24, 2013:
Lek did a great job on the port topsides, working all by himself as he wet‑sanded with 400, 600, 800, and 1200 grit paper, repairing the inevitable small gelcoat defects along the way.  Jon started sanding the gelcoat at the waterline, fairing it into the hulls.  This turned out to be a tough job that he eventually handed off to Nut.  He also spent time polishing the mast spreaders and finger sanding the fiddly bits at the base of the mast.  Houa built up some 4‑layer sound insulation and glued it to the undersides of both engine hatches.  He reinforced the starboard aft bed and replaced all of the headliner supports in all 4 cabins, modifying them to go around our new hatches.  Then he started removing some of the damaged wood from the middle of our old cockpit table.  Baw, Nut, and Pla spent much of the week wet‑sanding under the bridge‑deck, another difficult job.  But on Friday they were able to polish the aft section, which lifted everyone's spirits.  Bank and Yoong wet‑sanded the insides of the topsides, making good progress.  Sue sanded much of the mast 1‑handed, but making great progress, and on Sunday she and Jon were able to paint Nyalic from the 2nd spreader down to the rope‑clutches.  Amanda spent much of the week chipping away at poorly adhered gelcoat on top of the cabin, a distressing discovery.  The yard buried a tire with a rope around it for us, giving us a better support for our tent.

2 strips of teak, held by wedges, being epoxied into the table
2 strips of teak, held by wedges, being epoxied into the table

Week 73, March 25 - March 31, 2013:
Boy and his wife Kit started working for us - a delightful, hard working and talented couple who speak English pretty well.  Kit did intricate detail work on the mast and then jumped down into the port engine room and cleaned it thoroughly.  Boy helped Jon remove and replace the 4 toilet‑out sea‑cocks and also went with Jon on a great spending spree, buying lots of plumbing fittings in town.  Jon used those fittings to put together a pair of diesel manifolds for the new forward tanks, and also cut out and de‑cored 2 engine‑room vents and the 2 aft shower holes, and drilled out and installed 12 PVC nipples in the cockpit that will become 6 more cockpit drains..  Houa bought teak planks for the cockpit table and started tearing apart the 2 sides that need work, epoxy sealing the good wood and gluing new teak into one of the sides.  On Tuesday a pickup truck pulled out right in front of Jon, causing him to smash into the side of the pickup.  Jon was not badly hurt, but the scooter needed work, which the driver's insurance company paid for.  Lek continued wet‑sanding the port topsides and then joined Pla and Nut sanding off the repair bumps from the starboard topsides.  The rest of the team spent much of the week chipping off poorly adhering gelcoat from the deck and cabin‑top.  The problems are more extensive than originally thought, so we've decided to have AME prepare the cockpit and sugar‑scoops, so they'll take full responsibility for everything working.  Unfortunately, some miscommunication caused them to only come 1 of the 3 days they were planning to.  Amanda's college house‑make Liz visited so Amanda didn't come in much this week, preferring the beaches and bars of Phi Phi Don, but she and Sue did get 2 layers of Nyalic on most of the spreaders as well as the base of the mast.

Jon's birthday dinner party - MUCH more food came out later
Jon's birthday dinner party - MUCH more food came out later

Week 74, April 1 - April 7, 2013:
A productive week.  Jon made up and installed 2 diesel fuel manifolds up forward, next to our new tanks, and 2 back in the engine room.  Jon also replaced the fiberglass rods in our trampoline supports with longer rods of the correct size.  Amanda joined Jon in assembling the mixing valves for the bathrooms.  Houa finished epoxying in teak planks into our cockpit table and the 2 halves were wrapped up and stored.  Then he started repairing the teak lattice between our trampolines.  Pla and Lek moved around the topsides, filling gelcoat pinholes and wet‑sanding with ever finer grades of sandpaper.  Baw and Yoong, and Nut and Bank before they left the team, scraped off almost all of the gelcoat that had been sprayed on the decks, a huge job.  Sometimes it was underlying filler that came off, but sometimes it was just the gelcoat, obviously sprayed on inadequately prepared surfaces.  Baw and Yoong then sanded the edges to fair everything in, and put down thick vinyl where the nonskid will go so they know where to walk and where not to walk.  P'Wat showed up to prepare the cockpit and sugar‑scoops, but he also didn't prepare the (epoxy) sugar‑scoops adequately, and the filler he put down was very soft, so Mike took over those jobs.  Hem, our mechanic, arrived and removed the raw water pumps from the engines so he could install better impellers and seals.  Sue finally got her cast off, but her arm still hurts and she can't work with it much, although she documented our progress and sanded some mast bits.  The filler on the transoms was ground off and replaced with several layers of fiberglass and phenolic filler.  Amanda continued polishing the forebeam and the spreader bars.  On Sunday the spreader bars got a good coating of Nyalic, and much of the mast got a second coat.

The valve cover-plate had to be trimmed down to fit, but it's in!
The valve cover-plate had to be trimmed down to fit, but it's in!

Week 75, April 8 - April 14, 2013:
Hem, our diesel mechanic, finally returned to finish a couple jobs that Jon wanted done - rebuilding the salt‑water pumps with the correct Yanmar parts and installing our 2 new Jackmaster bypass oil filters.  Jon spent a lot of time in the bathrooms, installing the new water mixing‑valves for the sinks and showers.  He also repaired an area where water was getting in back at the transoms.  Yoong and Baw and Nut sanded virtually all of the deck and cabin‑top, smoothing down the edges of the chipped‑off gelcoat and applying filler where necessary (and being extra careful about cleaning and adhesion).  Then they moved on to sanding some of our hatches and cleaning the fo'c's'les and grinding underneath our keels and washing the underwater areas in preparation for the epoxy barrier coats.  Phuket Fiberglass delivered 50 liters (13 gallons) of epoxy for that underwater barrier coat.  Lek and Pla finished the pinhole repairs and sanded the topsides up to 1500 grit, then they cleaned and painted the undersides of the engine hatches.  Sue and Amanda worked on polishing the forebeam and the anchor support beam, and Sue spent a lot of time in the apartment, working on our taxes.  We turned the mast on its back and started cleaning up bits of mast hardware.  Houa spent the week rebuilding the teak grate that goes over the anchor support beam, between the trampolines.  Mike brought a team to prepare the swim‑platforms for gelcoat, and spread some soupy epoxy on to level them out.

Houa finishing up the assembly of our teak lattice
Houa finishing up the assembly of our teak lattice

Week 76, April 15 - April 21, 2013:
Houa finished most of the hard work on the teak lattice that goes between Ocelot's trampolines - cutting out the teak strips, routing them out, fitting them together, and epoxying them into their frame.  He also added more teak and ash (no holly here) to one of our floorboards.  Baw and Pla prepared much of the cockpit for gelcoat, sanding and filling all the many fiddly bits.  Jon found that some serious work was needed on the floor of the cockpit lockers so Baw and Pla ground off the bad gelcoat, then removed and replaced some delaminating glass.  Lek sanded the helm seat and the engine hatches, getting them ready for gelcoat.  Then he built up and painted the edges of the cockpit hatches, to better support the teak that will go on top of them.  Lek and Pla spent some time on the cabin‑top, filling dips and sanding chipped edges smooth.  Amanda rough polished the anchor support, boom, and forebeam, but then a grinder attacked her so she moved over to help Jon on the mast.  They untangled and rearranged the halyard chaser lines in the mast and pulled all of the main PVC wiring conduit sections up the mast.  Our new Dynex Dux diamonds need special mast fittings, so Jon opened up 8 thimbles to put over spreader‑tips.  With the changing monsoon, Jon reinforced our tent supports for SW winds.  Sue dug out our mast bits and started cleaning them up, helped rough polish the spars, and also helped Jon with the mast wiring conduits.

The 4 starboard side templates on the 4 sugar-scoop steps
The 4 templates on the 4 starboard sugar-scoop steps

Week 77, April 22 - April 28, 2013:
A major change of direction - Mike (AME) agreed that instead of spraying gelcoat around where the nonskid will go, then sticking the nonskid down and then spraying more gelcoat around the edges, it would be simpler if the nonskid went down first and then he could do a heavy spray of gelcoat around the edges of the nonskid.  This would save lots of masking and sanding, give us one fewer layer on the deck, and probably save all concerned both time and money.  So Baw and Team Hacking spent the week preparing for the nonskid - marking off the borders of where it will go, smoothing the existing deck, laying parallel alignment lines down the deck, and building the first 10 templates for Mike to use for cutting out the nonskid panels.  Ben and Lek worked under Ocelot, sanding and painting the undersides of the cockpit hatches and the shelves from the scuba locker and the fo'c's'les.  Houa finished both the teak lattice and the broken floorboard he's been working on.  He put gaskets on the engine hatches so they could be put back in place, cut 3 sheets of 3mm plywood into thin strips for the templates, routered out the areas for the swim‑ladder hinges, and made 10mm plywood covers for the other 14 deck hatches so we won't risk falling through one.  Pla worked on the cockpit lockers, putting a thick layer of epoxy filler and some glass on the floor, and spreading polyester filler on the walls to smooth them out.

Houa planing a nice face on one of his big teak boards
Houa planing a nice face on one of his big teak boards

Week 78, April 28 - May 5, 2013:
Work focused on 3 areas this short, Labour Day week: our new teak, the cockpit, and the nonskid for the deck.  Houa bought $2,000 of big teak blocks and spent the week making expensive sawdust - cutting the teak into strips for the teak floor in the cockpit, planing the strips flat, and routing a groove in the edges.  He ended the week with 75 nicely planed and prepared teak boards ready to cut down to size.  Baw, Pla, and Lek spent much of the week in the cockpit, preparing it for Houa's teak, measuring the edging and building it up where necessary, filling the bottom so it's flat and the right height, and sealing the filler with waterproof epoxy resin, all to Houa's exacting specifications.  They also cleaned out the dive and rope locker, and epoxy sealed the frames that hold the shelves up in there.  Jon and Amanda laid out exactly where many of the nonskid panels will go on the deck, and made careful templates of the first 32 areas, almost half of the 75 templates we'll need.  This is a frustrating job, as they need to plot where the deck hardware will go, and they've got to show how all the nonskid diamonds need to line up, when Ocelot has very few straight lines.  Baw's brother Ben spent most of the week in the port fo'c's'le, sanding and cleaning it to paint.  Sue, our photographer, split her time between taking pictures and polishing the forebeam supports, the anchor beam support, and the forebeam itself, which she was able to Nyalic on Sunday.

Laminating strips of teak together in a curve for the eyebrows
Laminating strips of teak together in a curve for the eyebrows

Week 79, May 6 - May 12, 2013:
Some good achievements this week.  Houa built a beautiful pair of curved, laminated teak rain‑gutter eyebrows, one to go over the entryway and the other over the galley window.  Each has several improvements over the originals.  Houa also made 3 teak mounting blocks to replace the old plywood ones under our spinlocks and turning‑blocks.  Pla and Baw repaired the last of the whale damage in the port engine room.  Then they ground back and reinforced 5 of the 8 areas around the rudder‑tubes with 4 layers of fiberglass (with Jon doing the last 3 areas).  The fiberglass still needs to be sanded and painted.  Baw and Lek spent much of the week preparing the cockpit for gelcoat spray, scheduled for next Monday.  This is a high priority so Houa can start laying down the teak flooring in the cockpit.  Dui and Ben and Pla had the really grotty jobs - smoothing the old gelcoat in the fo'c's'les and the chain lockers, to prepare them for painting.  Jon and Amanda spent much of the week drawing out exactly where we want the nonskid to go on the foredeck, and making up templates so Mike can cut the nonskid to the correct shapes.  As part of that they found where a reefing pad‑eye has to go at the base of the mast, and ground back the filler so it could be mounted flat.  Jon de‑cored the anchor‑winch bolt‑holes, but they still need to be filled.  Sue made good progress polishing spars and sorting and cleaning bits and pieces.  With Amanda she took a complete inventory of the bits stored in our apartment.  Team Hacking also worked out now many mast steps we want (27) and where they need to go.

Thai Refit: Up | Thai Refit Summary | Week #79 | Week #78 | Week #77 | Week #76 | Week #75 | Week #74 | Week #73 | Week #72 | Week #71 | Week #70 | Week #69 | Week #68 | Week #67 | Week #66 | Week #65 | Week #64 | Week #63 | Week #62 | Week #61 | Week #60 | Week #59 | Week #58 | Week #57 | Week #56 | Week #55 | Week #54 | Week #53 | Week #52 | Week #51 | Week #50 | Week #49 | Week #48 | Week #47 | Week #46 | Week #45 | Week #44 | Week #43 | Week #42 | Week #41 | Week #40 | Week #32 | Week #31 | Week #30 | Week #29 | Week #28 | Week #27 | Week #26 | Week #25 | Week #24 | Week #23 | Week #22 | Week #21 | Week #20 | Week #19 | Week #18 | Week #17 | Week #16 | Week #15 | Week #14 | Week #13 | Xmas Break | Week #4 | Week #3 | Week #2 | Week #1

Ocelot Pages: Ocelot Layout | Ocelot's Deck | Cockpit Photos | Inside Ocelot | Kronos 45 Specs | Modifications | Refrigeration | Venezuela Haul Out | Tonga Haul Out | Thai Refit

Top Level: Home | Destinations | Cruising Info | Underwater | Boat Guests | Ocelot | Sue | Jon | Amanda | Chris | Site Map | Make a Comment


This site is
sponsored by:
The Triton - Nautical News for Captains and Crews

Copyright © 2000‑2013 Jon and Sue Hacking -- HackingFamily.com, svOcelot.comAll rights reserved.